This website uses proprietary and third-party cookies. By continuing to navigate this website, you are accepting the use that we make of them. If you wish, you may change your settings on your browser.

What are you searching?

    Krobia I - Poniec II wind farms

    Clean energy for more than 80,000 homes in Wielkopolskie (Poland)

    Krobia I and Poniec II wind farms are two twin wind farms featuring 21 wind turbines in total able to produce enough clean energy from wind to power more than 80,000 homes, thus avoiding the emission of 154,000 metric tons of CO2 a year. Each of the ACCIONA Windpower technology wind turbines has 3MW rated capacity and 116m rotor diameter mounted on 120-meter-high concrete tower. Owned, built and operated by ACCIONA Energy, both wind farms make 63 MW of installed capacity. The company also has another wind farm in Poland –Golice (38 MW)- located in the Lubuskie province.

    POLISH VERSION

    GENERAL INFORMATION

    Location
     Municipalities of Krobia and Poniec, Wielkopolskie (Poland).
    Capacity
    33 MW (Krobia I) and 30 MW (Poniec II).
    Wind turbine
    ACCIONA Windpower AW 116/3000.
    Tower
    Concrete, 120-meter hub height.
    Start-up
    2013 / 2015.
    Owners
    ACCIONA Energía Internacional

    KEY POINTS

    • ACCIONA Windpower turbines, ideal for medium-speed winds, with a rotor diameter of 116 meters on a tower with a hub height of 120 m
    • Average annual production: 160 GWh, equivalent to the consumption of around 80,000 homes.
    • CO2 emissions avoided: 154,000 metric tons/year from coal-fired power stations.
    • Project based on detailed technical studies to minimize its impact on the environment
    • Successfully built overcoming harsh winter weather conditions.